Seasonal commissioning
The CIBSE Commissioning Codes generally use the following description to define ‘commissioning’: ‘The advancement of an installation from the state of static completion to full working order to specified requirements. It includes the setting to work of an installation, the recording of set values and performance for future reference, and the regulation of the system.’
The concept of seasonal commissioning recognises that some aspects of the systems need to be commissioned when the external temperatures and indoor occupancy patterns are close to the peak conditions for which the system was designed.
Seasonal commissioning is the performance evaluation of a building and its engineering services under full load conditions during peak heating and cooling seasons, as well as part-load conditions in spring and autumn.
Ref Seasonal Commissioning (BG 44/2013), written by Sands J and published by BSRIA in January 2013.
NB BG 88 Commissioning Responsibilities Framework, by Matt Lowry, published by BSRIA in January 2025, defines seasonal commissioning as: ‘The performance evaluation of a building and its engineering services under full load conditions during peak heating and cooling seasons, as well as part-load conditions in spring and autumn.’
--BSRIA
[edit] Related articles on Designing Buildings
Featured articles and news
ECA support for Gate Safe’s Safe School Gates Campaign.
Core construction skills explained
Preparing for a career in construction.
Retrofitting for resilience with the Leicester Resilience Hub
Community-serving facilities, enhanced as support and essential services for climate-related disruptions.
Some of the articles relating to water, here to browse. Any missing?
Recognisable Gothic characters, designed to dramatically spout water away from buildings.
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.